Facilities
HONG KONG

Valuetronics Holdings
Unit 9-11, 7/F
Technology Park, #18
On Lai St.
Shatin, New Territories
Hong Kong
CHINA CAMPUS

Long Shan 2nd Road, Western District of Science and Technology Park,
Daya Bay Economy and Technology Development District,
Huizhou City, Guangdong Province, PRC
Postal code: 516081
VIETNAM CAMPUS

Plot No. C14-15-16-17, Thang Long Industrial Park (Vinh Phuc),
Thien Ke Commune,Binh Xuyen District,
Vinh Phuc Province, Vietnam


Located in same reputable Japanese run Industrial Park as Phase I.
Factory size: 550,000 square feet
Year 2021: End/Jul Status

Year 2021: End/May Status


Year 2021: End/April Status

Year 2021: End/March Status


Year 2021: End/February Status


Year 2021: End/January Status


Year 2020 : End/December Complete of Roof Work

Year 2020 : December Complete Superstructure Work & Topping out ceremony




Year 2020 : November 3rd Floor Construction

Year 2020 : October 2nd Floor Construction

Year 2020 : September 1st Floor Construction

Year 2020 : August Civil Construction started

Year 2020 : July Groundbreaking Ceremony

Year 2020 : February Site Piling

Year 2019 : November Geological Survey

Year 2019 : October Land Acquisition